Header image  
Your Engineering Solutions...Start to Finish
 
    ::  
 

Construction Status for IPFW Pedestrian Bridge

Below are some of the pictures of the progress for the IPFW Pedestrian Bridge project.  This page will be updated as often as possible with new pictures and the project status.
POSTED: November 4th, 2008
It's been a while since the last update, and the bridge is almost a bridge.  The first two decking sections are up and poured on both the east and west sides, and the third beam section is attached to the west side.  This week we should be seeing another beam section go up on the east side.  The piece to go up this week will be one of two remaining sections that need to be placed.  The final beam section will be attached after final measurements, and the correct shims can be added.  This will most likely happen by the end of the month, and hopefully a couple of nice days of weather will allow the full deck to be poured.
Below are pictures of the work performed since the last update.  More pictures will be updated later this week with decking and additional beam section.
Also thanks to Bob Addison of R.L. McCoy for these two aerial shots of the bridge.
East Side Wall East Side Wall
East Side Wall East Side Wall
East Side Wall
POSTED: October 10th, 2008
After a couple of productive days, the pylons are finally up in the air and secured.  The pylons went up on Wednesday after some initial struggles, and then the cables were attached on Thursday.  Final preparations are being made today for the elevations on the steel and pylons, then metal decking will be welded down.  Before the decking is poured, the east side pylons will be set.  This is scheduled to take place next week Wednesday, and should be finished up by Friday.  The decking will most likely be poured the following week, after the iron workers have had time to place the decking and steel reinforcing in.  The bridge is still on schedule to be completed by next year, and the structure itself should be fully erected by the time winter rolls around.  Concrete decking will most likely not be finished by this year, but some of it will definitely be poured.
Below are pictures of the newly erected pylons and of work performed since the last update.
East Side Wall East Side Wall
Pylons Pylons
Pylons Pylons
Pylons Pylons
Pylons Pylons
Pylons Pylons
Pylons Pylons
Pylons Pylons
Pylons Pylons
Pylons
POSTED: September 29th, 2008
September is nearly over, and progress has continued on the bridge.  The second pier has been finished, and the west side has seen a lot of steel.  The hangers on the west abutment are now in, and the final wall section was poured.  This means that the bridge is days away from having the first set of pylons being set.  This operation is scheduled to happen on the 2nd of October (this Thursday), and will most likely carry into Friday.  On Thursday the pylons will be set, and then on Friday a second section of still will be added.  This week should also see structural steel being placed on the east side abutment and pier.  The east side could possibly be see the pylons being set by mid October, and then decking sometime between October and November.  Currently the bridge is on track to have all the structural steel placed before the winter weather shuts down the job site. 
Below are pictures are work performed since the last update.
East Side Pier East Side Pier
Steel West Side Steel West Side
Steel West Side Steel West Side
Steel West Side Steel West Side
POSTED: September 12th, 2008
It's now September, and the bridge is starting to really come together.  The west side is getting prepared to get the first section of structural steel, and the first pylon is now delivered to the site.  Next week this steel will be placed, and then about 2 weeks from then the first pylon will be seen in the air.  This time line for the pylon being erected is pure speculation currently, and they could potentially be on the ground until next year.  Next week should also have the concrete pour for the second pier, bringing the east side all that much closer to gearing up for structural steel.  Look for bridge decking to be poured in October, and again in November.
Below are pictures of work performed since the last update.
Piling Piling
Piling Piling
Pier Pier
Pier Pier
Pier Pier
Steel Delivery Steel Delivery
Steel Delivery Steel Delivery
POSTED: August 22nd, 2008
August is winding down, and much has been accomplished on both sides of the bridge.  On the west side the pier has been completely poured, and is awaiting the pylons and structural steel.  On the east side the abutment has been poured, the walls have been poured, and the cofferdam is on its way to completion.  By the middle of next week it looks like the piling should be installed in the pier, and the steel reinforcing should be in place.  This should place the footer being poured in the second pier by the beginning of September, and then another couple of weeks for the pier.  Depending on the time the final wall section might be going up on the abutments, and then not too long after that some decking.  This should happen sometime in September/October.
Below are pictures of work that has taken place.
Pier Pier
Pier Pier
Abutment Walls Abutment Walls
Abutment Walls Abutment Walls
Abutment Walls
Cofferdam Cofferdam
POSTED: August 8th, 2008
July has ended and McCoy is on the other side of the river.  The second abutment footer is poured, and the wall section for the first pier is poured as of today.  Within the next week or so the wall for the second abutment could possibly be poured as well.  The causeway has yet to be constructed, but should be placed within the next couple weeks.  McCoy looks to be on schedule, and by the end of the construction season look for some bridge decking to be up.
Below are pictures of work that has taken place.
Pier Pier
Excavation Excavation
Piling Piling
Piling Piling
Reinforcing Reinforcing
Abutment Footer Abutment Footer
Pier Pier
POSTED: July 30th, 2008
Form
POSTED: July 28th, 2008
July is nearly over, and McCoy continues to make progress on the IPFW pedestrian bridge.  The piling for the piers is in, and so is the pier footing.  Throughout this week the arch form will be installed, and then perhaps by Friday another pour will take place.  There's a lot left to do on the west bank, but it might not be too long until the work moves over to the east bank.  With the weather still cooperating perhaps some bridge decking could be seen going up in the not too distant future.  The causeway should be going in the next couple of days/weeks, and with that boaters in the area should be aware of the potential hazard.
Below are pictures of work that has taken place.
Excavation Excavation
Drainage Layer Drainage Layer
Piling Piling
Piling Piling
Piling Piling
Grounding Grounding
Grounding Grounding
Grounding Grounding
Reinforcement Reinforcement
Pier Footing Pier Footing
 
       
  Back to Top  
  ©Copyright 2005-2008 A&Z Engineering, LLC. All rights reserved