St. Joe Center Road, Fort Wayne, IN | |
|
This project involves; widening St
Joe Center from 2-lanes to 4-lanes of new concrete pavement; installation of new storm sewers; new street lighting;
sidewalks; curb and gutter; and a new traffic signal. Key Inspection Staff: Jamal Anabtawi, Mark Voss, & Chris Franz Project Costs Status: Phase I-45% (Completed) Project status page can be viewed here. |
||
![]() |
IPFW University Pedestrian Bridge Over St. Joe River, Fort Wayne | |
|
Beginning in June 2008, the second IPFW bridge will span St. Joe River.
This project will serve to connect the east and west sides of St. Joe River for
to the future hotel, parks, and retail area. Key Inspection Staff: Jamal Anabtawi & Chris Franz Project Costs Status: 2008 Progress-55% (Completed) Project status page can be viewed here. |
||
| Back to Top |
|
Upcoming Inspection Projects |
||
![]() |
Waterloo Historic Depot, Waterloo, IN | |
|
Slated to begin in 2008, the historic Waterloo Depot
will under go a complete restoration.
This project will serve to provide people traveling on Amtrak with
an enclosed shelter, and to promote growth around downtown Waterloo. Key Inspection Staff: Jamal Anabtawi & Chris Franz |
||
![]() |
Bridge 60 Replacement, DeKalb County, IN | |
|
Scheduled to begin early spring of 2008, this project will replace the bridge the is slowly deteriorating while seeing
an increasing amount of truck traffic. The new bridge will consist
of two 12-foot lanes, and two 6-foot concrete paved shoulders. This project will also lead the way for the improvement project scheduled to begin in
the summer of 2008,
which will improve the substandard intersection of CR 59 and SR 8. Key Inspection Staff: Jamal Anabtawi & Chris Franz |
||
| Back to Top |
|
Completed Inspection Projects |
||
|
|
Bridge 103 Replacement, DeKalb County, IN | |
|
This project consisted of replacing the existing bridge with: two 12-foot lanes and two 6-foot shoulders; and new guard rail.
Key Inspection Staff: Jennifer Sharkey & Chris Franz Project Cost: $0.40 million |
||
|
|
Allen County War Memorial Coliseum - Coliseum Bld. SR 930 New Entrance | |
|
A&Z's first construction inspection project was, that of S.R. 930 entrance project for the Allen Country War Memorial Coliseum. The project consisted of widening and adding travel lanes, storm sewer, new traffic signal, and new roadway alignment. A&Z inspection responsibilities included:
This project was completed on September 21st, 2007 Project Cost: $2.2 million Key Inspection Staff: Mark Voss, Chris Franz & Jennifer Sharkey |
||
|
|
Waterloo Water main Relocation, Waterloo, IN | |
|
This project involved the relocation of 2 fire hydrants, reconnecting 6 residences and 200 linear feet of water main. Responsibilities of the inspector were:
Key Inspection Staff: Chris Franz |
||
![]() |
Allen County ADA Inspection | |
|
A&Z Engineering assisted Allen County during the summer of 2005 by taking a part in a survey of several subdivisions to check for compliance of sidewalks. The responsibilities for the inspector on this job included:
Key Inspection Staff: Chris Franz |
||